The principal conclusions are:
Significant cost is involved to address the fault level issue at the Energy Australia substation. As a minimum, a fault limiting device is required on the generator at an estimated cost of $350,000. This is a short-term measure until the longer-term issue of fault levels throughout Sydney CBD substations is addressed.
Shutdown of all customer supplies for a period of several hours will be required in order to carry out the generator connection. This may present planning difficulties.
The report also makes recommendations in regard to load monitoring, inspection of customer switchboards to clarify fault rating, determination of method for remote generator dispatch, and the long-term issue of fault levels in the Sydney CBD.
|