Project Title:  

On site generation PV factory commissioning tests

Energy Type:  

Solar – Photovoltaics

Client:  

BP Solar (for Ford Motors)

Location:  

Ford Motor Company Engine Plant Bridgend South Wales

Project Size:  

98kW

Project Scope:  

Econnect were responsible for testing the PV array connection inverters to demonstrate compliance with Distribution Code connection requirements, especially Engineering Recommendation G59.

Further project information:

Key Achievements:  

Achieved electrical acceptance testing for one of the first large scale building integrated PV systems in UK.

 

Completion Date:   Project commissioned 1998.

 