Earlsburn was the first wind farm site in the UK to install a Hybrid Statcom solution to allow Grid Code Compliance.
This equipment allowed a previously unviable project to go ahead as the turbines themselves were unable to operate between the voltage guidelines required in the Grid Code.
The static compensation equipment allows voltage control of the wind farm and this meets the Grid Code requirements. |